Abstract & Overview
This article presents various options available for the energy conservation both in new and in existing operating distillation units. Some of them can be implemented without much cost involved whereas some requires moderate to high capital investment. Therefore, various available options have been divided into categories depending upon the investment involved: (1) Nil to very nominal (Improvise in the operating conditions; Improvise in the maintenance); (2) Moderate (Waste heat recovery; Insulation; Replacement of internals with efficient device); and (3) High (Upgradation of instrument control system; Two stages condensation; Split column operation; Heat pumping; Intermediate reboilers and condensers). Options involve nil to nominal investments can be tried in the operating units. The moderate to high investment options should be tried in both new designs as well as existing units after technoeconomic study to justify the capital expenditure and pay-off period.